Progress draws every 30 to 60 days. MCA debits every business day. We close the gap.
Construction cash flow runs on draw cycles. Stacked MCAs run on a daily clock. We restructure so the program respects the draw calendar and protects your bonding capacity.

Why MCAs hit construction hard
Construction sees stacked business debt across MCAs, bank lines of credit, equipment finance, and vendor and supplier debt. Each layer has its own enforcement playbook and its own cash flow risk.
The first reason is progress payment timing. A residential remodel GC might submit a draw at 30 percent completion, wait 21 days for inspection and approval, and then wait another 14 days for the wire to clear. That is a 35 day cycle on a single draw. Meanwhile the daily MCA debit has hit 25 times. Bank LOC payments are monthly. Equipment finance on the bobcat and the dump truck is monthly. The math only works when the draw cycle is faster than the daily debit accrual, and it almost never is.
The second reason is bank LOC concentration. Most established contractors run on a bank LOC for working capital. The LOC funds mobilization, materials, and labor during the gap between project start and first draw. When draws slip and the LOC runs to its limit, the contractor stacks an MCA or two to bridge the next project. The bank LOC then hits its covenant threshold, and a bank workout becomes the urgent issue while the MCAs keep debiting.
The third reason is non-paying GCs and vendor cascade. A single GC slow-paying or stopping payment on a $200,000 receivable can take down a sub. The sub stacks MCAs to keep the crew paid and the next project moving. Material suppliers, who were already running 30 to 60 day terms, see the activity and tighten credit, sometimes filing mechanic's liens. Vendor debt then becomes a parallel workout to the MCA and bank exposure.
The fourth reason is heavy equipment finance. Bobcats, dump trucks, excavators, bucket lifts, and specialty equipment are usually financed through equipment lenders at $80,000 to $400,000 per piece. A typical mid-sized contractor carries $500,000 to $2 million of equipment finance. When cash tightens, equipment payments compete with everything else, and acceleration on one piece can cross-default the whole equipment portfolio.
The fifth reason is bonding capacity sensitivity. Sureties review the contractor's credit profile, working capital, and outstanding liabilities before bonding the next project. A stacked MCA position, a covenant violation on a bank LOC, or an equipment acceleration all show up in the surety review and shrink bonding capacity at exactly the moment the contractor needs more bonding to take on better work.
The sixth reason is material price volatility. Lumber, steel, copper, and concrete pricing can move 20 to 40 percent in a single quarter. When suppliers demand deposits and prices spike mid-project, the contractor either eats the loss or stacks an MCA or LOC draw to bridge the gap.
What we hear from construction merchants
- Progress draws arriving every 30 to 60 days against daily MCA debits that never miss
- A single non-paying GC turning into 3 to 5 stacked MCAs over a year
- Subcontractor invoices and lien deadlines stacking with daily lender pulls
- Mobilization costs hitting before the first draw clears the bank
- Retainage held until project closeout while MCAs keep debiting at full pace
- Bonding capacity at risk if total liabilities and credit profile move the wrong direction
- Material price volatility and supplier deposit demands eating working capital
Common stack patterns
Construction MCA cases share a recognizable shape, and the timing usually traces back to either a non-paying GC or a single oversized mobilization.
- Stack count: 3 to 5 active MCAs, with 6 or 7 on heavier cases
- Time to stack: 12 to 24 months from first advance to landing on our desk
- Factor rates: 1.30 to 1.45 across most cases
- Daily debits: $800 to $3,000 in combined daily withdrawals
- Average face balance: $400K to $850K combined
- Trigger event: Either a single non-paying GC, an oversized mobilization on a project that ran long, or a material price spike on a fixed-price contract
The bonded contractor cases are different from the unbonded cases. Bonded contractors usually have stronger credit profiles, slower stacking patterns, and a higher average debt size. Their programs lean toward restructure rather than settlement because the credit profile preservation matters more.
The unbonded cases are typically smaller residential GCs, remodelers, and trade subs. Their stacking patterns are faster and their settlement leverage is higher because they have less to lose from a credit profile event.
How the practice works with you
Construction cases get a draw-cycle-aware approach because the cash flow shape is so different from other verticals.
Step one: bonding and credit profile review. At intake, we identify whether the operator is bonded and how active the surety relationship is. If bonding is active, the program is designed to preserve the credit profile the surety reviews. That usually means leaning toward restructure rather than settlement on the largest advances.
Step two: draw calendar mapping. We map the operator's actual draw calendar across active and pipeline projects. Settlement and restructure payments are then sequenced to fall after major draws clear, never before. This is the core difference between a construction program and a generic MCA program.
Step three: lien and subcontractor protection. Subcontractor payments stay current through the program. Mechanic's lien rights and notice deadlines are protected. Where the operator has lien rights against a non-paying GC, we sequence the MCA work to preserve those rights.
Step four: parallel reconciliation. Reconciliation requests go to all active MCA lenders simultaneously. The daily debit usually pauses within 3 to 6 weeks of the first reconciliation, slightly longer than other verticals because lenders sometimes contest reconciliation in construction cases.
Step five: surety coordination where applicable. If a major project requires a new bond during the program, we coordinate with the surety in advance. The program timing can be structured around bonding deadlines so the next project does not get blocked.
A typical construction case
Contractor: Residential remodel GC, 12-year history, average project size $150K to $400K, operating in two metro markets with a crew of 8 plus 12 active subs.
Stack at intake: 4 active MCAs with combined face balance of $590,000. One reverse consolidation lender. Average daily debit total: $2,650.
Trigger event: A custom kitchen and bath remodel ran 11 weeks long on a fixed-price contract due to permitting delays and a backordered Wolf range. The contractor took the first MCA to fund the overrun. Three more stacked over 14 months as a single GC stopped paying on a $180,000 receivable and the contractor's bond renewal got tight.
Program: Restructure on the largest advance to preserve bonding profile. Settlement on the other 3, including the reverse consolidation. Reconciliation requests filed in week 2. First settlement closed in month 5 at 41 cents. Reverse consolidation unwound in month 7. Restructure on the largest advance ran through month 13.
Outcome: Total payback of $313K against $590K face balance. Daily debits reduced from $2,650 to a single $11,500 monthly restructure payment. Program closed in 13 months. Bonding capacity preserved. Contractor restored to a $400K project size in month 14.
Industry-specific risks
Construction MCA cases come with industry-specific risks that the operator should understand before starting a program.
Bonding non-renewal. A surety review during the program can result in reduced bonding capacity or non-renewal if the credit profile moves the wrong direction. We design the program to protect the bonding relationship, but the operator should understand that bonding is sensitive to any change in the financial picture.
Mechanic's lien filings against the contractor. If subcontractors or suppliers feel their payments are at risk, they can file mechanic's liens against the contractor or against the active project. The program is designed to keep sub and supplier payments current, but the operator has to be transparent at intake about any sub or supplier relationships that are already strained.
Subcontractor payment chain breakage. When a contractor's cash flow tightens, the temptation is to defer sub payments. That breaks the chain. Subs find other GCs and the operator loses the labor that makes the next project possible. The program is built around keeping sub payments on time.
License renewal timing. Contractor licensing varies by state and includes financial and insurance requirements that have to stay current. We sequence the program around renewal dates so license status is never at risk.
Frequent questions from construction merchants
Will resolving MCAs put my bonding at risk?+
We coordinate carefully with bonding so the program does not jeopardize active jobs. Restructure programs are usually preferred for bonded contractors because they preserve the credit profile the surety reviews.
What about pending lien claims?+
Lien rights are time-sensitive and are protected through the program. We layer the MCA work around your lien calendar so deadlines are never missed. Mechanic's liens against the contractor by subcontractors are reviewed at intake.
What if my GC is slow-paying me right now?+
Slow-paying GCs are the most common trigger for construction MCA stacking. The program is built around the actual draw cycle, including the slow GC. We can also help with collection support on the receivable.
Can I take new jobs during the program?+
Yes. Most operators take new work during the program. Where bonding is required, we coordinate with the surety so the new job does not get blocked by the program timing.
Will my workers' comp and general liability insurance be affected?+
Insurance is non-negotiable and stays current through the entire program. The program is designed so insurance premiums are never the line item that gets skipped.
What about my material suppliers and equipment leases?+
Material supplier credit and equipment lease relationships are protected. The program operates on the MCA lender side and does not interrupt trade payments. Where supplier credit has tightened, we work to restore it as the program closes out.
Can you help with a payment dispute on a job?+
MCA work and payment dispute work are different but they sometimes overlap. If a payment dispute is the underlying cause of the MCA stack, we can coordinate with construction counsel where it matters.
What about my subcontractors who are owed money?+
Subcontractor obligations are protected through the program. Sub payments stay current. The program does not require deferring sub payments to fund settlement.
I have a confession of judgment from a New York lender. Now what?+
COJ filings are common in construction MCA cases. We coordinate licensed counsel in New York within 72 hours and parallel-track the COJ response with the broader settlement work.
Will this affect my license or registration with the state?+
Contractor license obligations are state-specific. MCA settlement does not directly affect contractor licensing as long as tax obligations and insurance stay current. We sequence the program around any license renewal dates.
Recent guides
MCA Debt Relief for Construction Contractors: Progress Payments vs Daily Debits
Construction cash flow arrives in draws and retainage; MCA debits leave daily. Why contractors stack advances faster than any other trade, and the relief sequence that protects bonding, liens, and the next job.
6 min read
Business Debt Restructuring in Florida: MCAs, COJs, and the Home-Court Advantages
Florida businesses carry more MCA debt per capita than almost anywhere. What Florida law actually says about confessions of judgment, account garnishment, homestead protection, and how restructuring plays out for Florida companies.
6 min read
Loans to Restructure Business Debt: When Borrowing Your Way Out Actually Works
Restructure loans promise one payment instead of five. Sometimes that is real: SBA refinances, term loans, asset-based credit. Often it is another MCA in disguise. The qualification math and the traps.
6 min read
What Is Business Debt Resolution? Every Option on One Page
Debt resolution is the umbrella over restructuring, settlement, consolidation, defense, and wind-down. A one-page comparison of all the options: cost, timeline, credit damage, and who each one actually fits.
6 min read
Get the weekly business-debt brief.
One email per week. New guides, working numbers, and case anatomies on business debt restructure. No filler.
No spam. Unsubscribe anytime.